Thanks guys,

Its the federate that getting changed on clicking cycle start after a feedhold (I'll run it again today to see if there are any other indicators) - oddly enough it only does the slower federate for one segment of operation (I think more than one line of code is run through) i.e. if my tool path is say doing a profiling cut first and then 4 pocketing cuts in the corners of the part and I feedhold during say one of the corner pocketing operations, it will do only that one at a slow feed rate and then the next segment and onwards run normally (after a rapid usually). Its like MACH has determined there was a feedhold and resume and is being cautious on the resumed operation before going at the job normally.

I certainly have a G94 line in, as you can see from the header in the job here:

( Roughing Out 8mmEnd )
( File created: Thursday, November 21, 2013 - 02:40 PM)
( for Mach2/3 from Vectric )
( Material Size)
( X= 202.800, Y= 153.500, Z= 40.000)
()
(Toolpaths used in this file:)
(Roughing Out 8mmEnd)
(Tools used in this file: )
(1 = End Mill {8 mm} TC 2Fl)
N100G00G21G17G90G40G49G80
N110G71G91.1
N120T1M06
N130 (End Mill {8 mm} TC 2Fl)
N140G00G43Z5.000H1
N150S10000M03
N160(Toolpath:- Roughing Out 8mmEnd)
N170()
N180G94
N190X0.000Y0.000F800.0
N200G00X-40.947Y-54.860Z5.000
N210G1Z0.000F100.0

I'm figuring its something in the way MACH is setup, but can't find it.