Very interesting thread. I'm with Sylyavski on this one and I don't think shrinking is that much. Considering the viscosity of the epoxy, pouring a few thin layers is not going to improve things much and I believe your'e better off with one thick layer. As an extreme example start with an uneven surface and try to paint layers it until its perfectly flat... But please carry on testing as its the one way we'll really know. Its difficult to test though as there are so many factors for example some epoxy likes to be cured cured at higher temps e.g. 60 or 80 deg Celsius so temperature might also have a big effect on the actual results.
-
29-12-2014 #2
Here are the "before and after" rail level measurements. That is, the results from the epoxy levelling (two curves, one measured going left to right and the other in the opposite direction, just to try to validate the measurement technique as obviously an error at one point will carry right through the remaining measurements). The third, flatter, curve is after shimming. Shims were calculated from the first pair of curves, and were to about the nearest "thou" as this was the thickness of the aluminium foil I used (with some 8 thou shimstock where it could be used). I could have used thinner foil but my wife wouldn't let me eat her Christmas chocolates which had thinner wrappers, even when I said that it was in the name of science and I wouldn't enjoy them...
Jonathan - just for you!
To calculate shrinkage, based on my hypothesis that this caused the variation in depth, I had three unknowns. These were S1, S2, and Z. These are the loss in height at the shallow end, the loss in height at the centre (deepest epoxy), and the shrinkage ratio expressed as final height/original "as poured" height. I could measure the depth of the epoxy bed at both points, and the drop in level between them. It was then just a matter of throwing together a set of three simultaneous equations in these variables and solving for each in turn. Plugging the values back in to the original equations gave the right answers, so I am assuming that my maths is OK. Obviously, the underlying assumptions might not be, but that's what we are exploring here.
Thread Information
Users Browsing this Thread
There are currently 1 users browsing this thread. (0 members and 1 guests)
Similar Threads
-
Self levelling epoxy resin
By flanagaj in forum Gantry/Router Machines & BuildingReplies: 5Last Post: 21-11-2020, 01:47 AM -
Epoxy granite or mineral casting
By mike mcdermid in forum Gantry/Router Machines & BuildingReplies: 46Last Post: 20-02-2014, 06:21 PM -
Epoxy Granite Molds?
By gavztheouch in forum Moulding MachinesReplies: 8Last Post: 18-02-2014, 07:28 PM -
Epoxy pouring advice
By cncJim in forum General DiscussionReplies: 12Last Post: 18-02-2014, 05:25 PM -
Epoxy cast plastic injection tools
By gavztheouch in forum Moulding MachinesReplies: 0Last Post: 27-01-2014, 11:33 PM



Reply With Quote

Bookmarks